Making Progress
By John Lux
A lot was accomplished today. Dennis & Dexter made a lot of progress getting the design & programming area fully connected to the Internet and within 24 hours they should be able to access our servers so that area will be fully functional. Sam & Rob continue to help out where they can testing connectors and running cable. The console in Audio B was put in and turned on and Rob’s already getting it set up.
We had our walk through with Beth & Megen from Spectra Contract Flooring this morning to go through the punch list of things that need tweaking. And we started talking flooring for the audio rooms. Speaking of the audio rooms, the design of the mix room has been locked and now the acoustical designer is doing sound testing to ensure everything is designed properly. We expect to be handing off to the architect within a couple weeks then quickly on to construction.